PRINCE2-7-Practitioner Sample Questions & Answers
Digs into the three PRINCE2 practices covering plans, organizing and the business case, the single biggest weight, then works through the seven processes, applying the seven principles, leading successful change, tailoring, and sustainability and digital data.
Launch the full PRINCE2-7-Practitioner simulator →Showing 10 of 20 free samples.
- Question 1Beginner
People Management · Integration of the people element
True or False: In a PRINCE2 7 project, the 'people' element is considered an integrated part of the method, influencing how principles, practices, and processes are applied, rather than being a separate, optional consideration.
Show answer & explanation
Correct answer: A
This statement is true. A key update in PRINCE2 7 is the integration of a central 'people' element. It's not a standalone topic but is woven into the fabric of the method, affecting how project managers should lead teams, engage stakeholders, and foster a positive project culture when applying all other parts of PRINCE2.
- Question 2Intermediate
Tailoring and Integration · Tailoring the 'Organizing' practice
A project to construct a new community center is being managed by a local council. The project is small, with a well-understood scope and a small, co-located team. The Project Manager is considering how to tailor the 'organizing' practice. Which of the following represents the most appropriate tailoring decision for this project's organization structure?
Show answer & explanation
Correct answer: C
Tailoring involves adapting the method to the project's environment, size, and complexity. For a small, straightforward project, it is common and appropriate to combine roles on the Project Board, provided there is no conflict of interest. If the budget holder (Executive accountability) is also the primary representative of the users, combining these roles is an efficient tailoring decision. This maintains the three essential interests (business, user, supplier) on the board without unnecessary bureaucracy.
- Question 3Beginner
PRINCE2 Principles · Applying 'learn from experience'
During the 'Closing a Project' process for a software development project, the team has produced a final Lessons Report. According to the 'learn from experience' principle, what is the primary purpose of this report?
Show answer & explanation
Correct answer: D
The 'learn from experience' principle is forward-looking. The primary purpose of the Lessons Report at the end of a project is to consolidate all lessons learned (both positive and negative) so that they can be reviewed and acted upon by the wider organization. This helps prevent future projects from repeating the same mistakes and allows them to adopt successful practices, thereby improving corporate capability.
- Question 4Intermediate
People Management · Managing team dynamics
A project manager is leading a team composed of individuals from different functional departments who have never worked together before. There are early signs of conflict over working styles and communication norms. To foster a collaborative and high-performing team culture, which people management technique would be most effective to apply early in the project?
Show answer & explanation
Correct answer: C
PRINCE2 7 emphasizes the importance of proactively managing team dynamics. Co-creating a team charter is a powerful technique that gives the team ownership of their working agreements. It allows them to collectively decide on communication methods, meeting etiquette, and how to handle disagreements. This builds trust and creates a foundation for effective collaboration, directly addressing the identified conflicts.
- Question 5Intermediate
PRINCE2 Practices · Applying the 'Risk' practice
A project's goal is to reduce a factory's energy consumption by 20%. The Project Manager has identified a risk that new environmental regulations, scheduled to be announced in three months, might require a 30% reduction instead. The probability of this is high. Which risk response strategy is most appropriate for the Project Manager to recommend?
Show answer & explanation
Correct answer: D
A contingent plan (or 'Prepare contingent plans' response) is the most suitable strategy here. The event is uncertain but has a high probability. It would be inefficient to immediately increase the scope and cost to aim for 30% if it's not required. Instead, the project should plan for the possibility. This involves identifying the actions needed to reach the 30% target and setting them aside to be triggered only if the risk materializes.
- Question 6Advanced
PRINCE2 Principles · Applying 'manage by exception' with change control
A project is experiencing frequent, minor requests for change from a key stakeholder. While each request is small, their cumulative effect is threatening the stage schedule. The project has an established change control procedure. How should the Project Manager apply the 'manage by exception' principle in this situation?
Show answer & explanation
Correct answer: B
The 'manage by exception' principle gives the Project Manager authority to manage the stage as long as it remains within the tolerances set by the Project Board. The correct application is to use the agreed change control procedure to assess and implement approved changes, while constantly monitoring the forecast against stage tolerances (time, cost, scope, etc.). As long as the cumulative impact of these changes does not threaten to breach tolerance, the Project Manager can continue to manage the situation without escalating to the Project Board.
- Question 7Beginner
PRINCE2 Practices · Applying the 'Organizing' practice
A university is launching a project to develop an online learning platform. The project will involve the IT department, several academic faculties, and an external software vendor. The Project Manager is defining the project management team structure. Which roles are essential to represent the three primary stakeholder interests on the Project Board?
Show answer & explanation
Correct answer: B
The PRINCE2 Project Board must represent the three primary stakeholder interests. The Executive represents the business interest (ensuring value for money), the Senior User represents the interests of those who will use the final product, and the Senior Supplier represents the interests of those designing and building the solution. These three roles are mandatory for a compliant Project Board structure.
- Question 8BeginnerSelect 2
PRINCE2 Practices · Applying the 'Plans' and 'Quality' practices
A project is using product-based planning to define the scope of a new marketing campaign. The team has created a Product Breakdown Structure (PBS) and is now writing Product Descriptions. Which of the following are key components of a well-defined Product Description? (Select TWO)
Show answer & explanation
Correct answers: C, D
The 'Purpose' section is critical as it explains why the product is needed and what it contributes to the overall project objective.
The 'Quality Criteria' are measurable definitions of the product's quality attributes. They are essential for quality checking and formal acceptance.
- Question 9Intermediate
PRINCE2 Processes · Managing a Stage Boundary (SB)
A Project Manager is preparing for an End Stage Assessment. The current stage has overspent its budget but is ahead of schedule. The Business Case remains viable. What information must the Project Manager provide to the Project Board to enable them to make a decision about authorizing the next stage?
Show answer & explanation
Correct answer: B
The 'Managing a Stage Boundary' process requires the Project Manager to provide the Project Board with two key pieces of information: 1) The End Stage Report, which shows how the completed stage performed against its plan (including the budget overrun and time gain). 2) The Stage Plan for the next stage, which details the plan for the upcoming work. This combination of past performance and future plans allows the Board to make an informed decision.
- Question 10Intermediate
PRINCE2 Practices · Applying the 'Issues' practice
A project is required to comply with new data privacy laws (like GDPR). This requirement was identified after the project was initiated. What is the correct sequence of actions within the 'issues' practice to handle this?
Show answer & explanation
Correct answer: A
This new requirement is a 'Request for Change' because it alters the project's baseline scope. The correct procedure is: 1. Capture it formally. 2. Examine its impact on the project's performance targets (cost, time, scope, etc.). 3. Propose options for dealing with it. 4. Escalate it to the appropriate level of authority (the Change Authority or Project Board) for a decision. 5. Implement the decision.